                   Lock Reconstruction Progress



The Appleton #1 lock has it's downstream doors removed and the mortar is being repaired
between the large cut stone blocks on the sidewalls. (closeup) The navigation canal is dewatered.

 
The Appleton #3 lock downstream of the Lawe St. bridge is getting site prep work done.
The canal is dewatered between #3 and #1.
 
The Old Oneida St. bridge is being sandblasted and painted.
 
Pictures Courtesy of: Dave Peck